Purchasing Of Waste Heat Boiler And Its Auxiliary Equipment For The New Construction Project Of Ziyang Gas Power Station Of Sichuan Investment Group

Jun 21, 2022 Leave a message

1) The second volume of the Technical Specifications of the Bidding Documents "Technical Specifications for Waste Heat Boilers and Their Auxiliary Equipment" Chapter 7.1 The dividing point of supply of each system of waste heat boilers is revised as follows:


2) The demarcation point of the steam pipeline is 1m outside the centerline of the outer column column near the gas turbine side of the auxiliary room, and the auxiliary room is located on the left side of the waste heat boiler (viewed from the gas turbine to the chimney). The design supply interface elevation of the steam pipeline It is tentatively set to be no higher than 15m, and finally confirmed in the design liaison meeting. Based on the principle of installing the least number of welding joints, for the pipes connecting the waste heat boiler with the steam-water pipes within the scope of the tenderee's design, the design institute selected by the tenderee shall assess the above pipelines. Carry out stress calculation to the outlet of each header of the boiler. The bidder is responsible for planning the direction of the above pipelines within the scope of the waste heat boiler, bearing the load of the pipelines within the steel frame of the boiler and auxiliary rooms, and designing the support and hanger (including the root, connecting parts, pipe parts) and the rooting of the support and hanger for the supply pipeline. Required steel structure. The header interface can bear the thrust and moment given by a certain thermal expansion of the pipeline, and the bidder shall provide its allowable value and thermal displacement value. The reaction force of the safety valve exhaust steam pipeline shall be the responsibility of the bidder and shall not be transmitted to the external steam pipeline. The expansion indicator in the furnace island area shall be a spring-type expansion indicator.


3) The demarcation point of the condensate pipeline is 1m outside the centerline of the outer row column of the auxiliary room steel frame close to the gas turbine side. The pipe joint should be able to bear the thrust and moment given by a certain thermal expansion of the pipe, and the bidder should provide its allowable value and thermal displacement value.


4) Closed cooling water system: The design and supply boundary is 1m outside the centerline of the outer column of the auxiliary room steel frame close to the gas turbine side. The bidder shall provide the closed cooling water consumption, temperature and pressure of all auxiliary equipment, as well as the pipe specifications and materials of the boundary interface.


5) The design demarcation point of compressed air system pipeline, high-side desuperheating water pipeline, nitrogen system, etc. is 1m outside the centerline of the outer row column near the gas turbine side of the steel frame of the auxiliary room. The pipe joint can bear the thrust and moment given by a certain thermal expansion of the pipe, and the bidder shall provide its allowable value and thermal displacement value.


6) The boundary point of the auxiliary heating steam pipeline of the deaerator is 1m outside the centerline of the outer column of the auxiliary room steel frame close to the gas turbine side.


7) The auxiliary room on the side of the waste heat boiler (ie: boiler feed water pump room) is designed by the bidder and the scope of supply: the auxiliary equipment room adopts a steel structure, and the equipment and pipes within the bidder's scope such as the water supply system are arranged on the zero-meter floor, and 2 ECA cooling units are used. Water pump (machine island manufacturer's equipment) and chemical water dosing room, etc. The middle layer is equipped with a frequency conversion room within the scope of the bidder and electronic equipment room, CEMS room, chemical sampling room, HVAC room and other rooms within the scope of the bidder, as well as steam and water pipeline support and cranes Rooting frame and other equipment; the load of the middle layer and above shall be provided by the tenderee to the bidder, and the bidder shall be responsible for the steel frame of the auxiliary equipment room (including the auxiliary steel beam of the auxiliary room brick wall and the floor) and the steel frame of the soda water pipeline support and hanger Structural design and supply.